Documented forum build · 964 · air-cooled

1990 964 Carrera 2 3.6 rebuild

A leaking 192,000-mile 1990 Carrera 2 progressed from an intended in-car reseal to a split-case 3.6-litre rebuild after a broken cylinder-three head stud was found, with owner documentation through first startup and an 8,000-mile follow-up.

Evidence: Opening thread page — reseal, broken stud and full-build decision · Page 2 — machining, rotating assembly and oil-system preparation · Page 3 posts 32–37 — case closure and Mahle piston-cylinder preparation · Page 6 posts 84 and 88 — installation and first-start result · Same-author post 3 — 8,000-mile rebuild follow-up

Vehicle
1990 Porsche 964 Carrera 2
Engine
1990 964 Carrera 2 3.6-litre flat six with 192,000 miles → Rebuilt 3.6-litre 964 flat six with new Mahle pistons and cylinders and reconditioned rotating components
Forum
Rennlist
Thread author
Meatball964 · 18 July 2017

Vehicle and engine evidence: Opening thread page — reseal, broken stud and full-build decision · Page 2 — machining, rotating assembly and oil-system preparation · Page 3 posts 32–37 — case closure and Mahle piston-cylinder preparation

Why it came apart

Multiple oil leaks prompted the reseal, but a broken cylinder-three head stud changed the plan to a top-end job and the mileage then led the owner to split the case for a complete rebuild.

Source: Opening thread page — reseal, broken stud and full-build decision

What the project aimed to do

Address the leaks and broken stud once, inspect the high-mileage bottom end and return the engine to long-term road service rather than repeat the removal later.

Source: Opening thread page — reseal, broken stud and full-build decision · Page 3 posts 32–37 — case closure and Mahle piston-cylinder preparation

Who did what

The owner performed their first engine drop and documented the teardown, preparation, assembly and installation with help from forum members; Ollie's handled specialist cleaning, inspection and balancing of the case, crankshaft and connecting rods.

Source: Opening thread page — reseal, broken stud and full-build decision · Page 2 — machining, rotating assembly and oil-system preparation · Page 6 posts 84 and 88 — installation and first-start result

The newly purchased C2 had 192,000 miles when the author began what was initially intended to be an in-car oil-leak reseal.

Vehicle context: Opening thread page — reseal, broken stud and full-build decision

Documented sequence

  1. Scope expansion and teardown

    The project moved from an in-car reseal to an engine drop, top-end rebuild and finally a split-case rebuild after the broken stud and high mileage were considered.

    Source: Opening thread page — reseal, broken stud and full-build decision

  2. Machine work and oil-system cleaning

    The case and oil passages were cleaned, the crankshaft was inspected and balanced, connecting rods were re-bushed and balanced with ARP bolts, and the oil tank, cooler and lines were removed for cleaning.

    Source: Page 2 — machining, rotating assembly and oil-system preparation

  3. Case and piston-cylinder assembly

    The case was sealed with Loctite 574 before new Mahle pistons and cylinders were weighed, cleaned and installed with their ring positions checked.

    Source: Page 3 posts 32–37 — case closure and Mahle piston-cylinder preparation

  4. Installation and first start

    The rebuilt engine, replacement dual-mass flywheel and associated parts were installed; the author then reported a successful first start after resolving a fan noise attributed to belt tension.

    Source: Page 6 posts 84 and 88 — installation and first-start result

  5. Mileage follow-up

    A later same-author Rennlist post reports approximately 8,000 miles on the rebuilt engine when the car reached 200,000 total miles.

    Source: Same-author post 3 — 8,000-mile rebuild follow-up

Named components and work

Reported outcomes

Forum-author-reported mileage follow-up

About 8,000 miles on the rebuild

In September 2019 the same author reported this mileage while marking the car's 200,000-mile total; no independent inspection accompanied the statement.

Source: Same-author post 3 — 8,000-mile rebuild follow-up

Evidence limits

  • The first-start and 8,000-mile results are forum-author reports and were not independently verified.
  • No dyno, final compression or final leak-down measurements were identified in the reviewed posts.
  • The complete M64 engine sub-code is not stated in the cited posts.
  • The 8,000-mile result appears in a later same-author Rennlist thread rather than the original rebuild thread.
  • Fresh automated requests to the main thread returned HTTP 403 from the forum's bot protection; the cited material was reviewed through public browser-indexed pages without authentication.

Access note: The thread pages and same-author mileage follow-up were publicly readable in browser-indexed forum pages without account authentication. Raw automated requests to the main thread met the forum's HTTP 403 bot protection when rechecked.

Reviewed source trail

  1. Opening thread page — reseal, broken stud and full-build decision · reviewed 2026-08-25
  2. Page 2 — machining, rotating assembly and oil-system preparation · reviewed 2026-08-25
  3. Page 3 posts 32–37 — case closure and Mahle piston-cylinder preparation · reviewed 2026-08-25
  4. Page 6 posts 84 and 88 — installation and first-start result · reviewed 2026-08-25
  5. Same-author post 3 — 8,000-mile rebuild follow-up · reviewed 2026-08-25